NEW CHROY CHANGVAR TEMPORAY BRIDGE

NEW CHROY CHANGVAR TEMPORAY BRIDGE

Cana-Sino Construction Corporation (CSCC), on 24 October 2017, celebrated the grand opening ceremony of this NCCTB Project Construction. This Company also acts as the main constructor for all process work of this temporary bridge. Moreover, since the start of construction, the phase of activities have been smoothly projected as planned.

NCCTB is the New Chroy Changvar Temporary Bridge Project where located across Tonle Sap River. It’s situated nearly to the planned New Chroy Changvar Bridge and also 2.5Km far from existing Cambodia-Japan Friendship Bridge in Phnom Penh, Cambodia.

Plus, This Bailey Bridge is mostly designed by using bailey frames and steel piles materials .The Dimension of the bridge is about 506.2m length, 12m width with two directions and 5 years of service life. The bridge roles so important to distribute traffic during repairing of Cambodia-Japan Friendship Bridge.

To sum up, by spending almost 6 months to challenge all obstacles with patience, strong commitment and efforts of CSCC team during this construction, This New Chroy Changvar Temporary Bridge was successfully completed on time and opened to use officially for Cambodian people on 08 May 2018 with the satisfied quality and safety.

Figure 1: Grand Opening Ceremony of Construction

cur-eve

Figure 2 : Location of Bailey Bridge

location_baltey1

Figure 3: Site Construction Area

Site-Construction-Area

Figure 4: Activity of Bailey Frame Construction

Activity-of-Bailey-Frame-Construction

Figure 5: General View of Bailey Bridge

Figure 6: Grand Opening Ceremony to Use the Bridge

Grand-Opening-Ceremony-to-Use-the-Bridge

Figure 7: Traffic on the Bailey Bridge

Traffic-on-the-Bailey-Bridge

Figure 8: NCCTB Team Construction

NCCTB-Team-Construction